Operations for the extended line to begin in Q4 2024
LRT-1 private operator Light Rail Manila Corporation (LRMC) has started the year with strong optimism as the LRT-1 Cavite Extension Phase 1 project reaches a significant milestone.
As of January 2024, the project boasts an impressive overall progress of 97%, solidifying LRMC’s bullish outlook for its target opening in the fourth quarter of this year.
“We are optimistic about the progress achieved in the LRT-1 Cavite Extension Phase 1 project. This significant milestone is a testament to the perseverance and dedication of our team and our contractors, all working together to make this project come to life connecting countless residents in the south of Metro Manila and nearby provinces,” LRMC President and CEO Juan F. Alfonso said.
Both civil and system works are progressing rapidly to ensure a smooth and timely opening. The five new stations are nearing completion, with Redemptorist Station at 93.3%, MIA Station at 93.5%, Asia World Station at 83%, Ninoy Aquino Station at 88%, and Dr. Santos Station at 94.1%.
Notably, Dr. Santos Station has completed staircase and louver installation. MIA Station has finalized its ceiling, and the station is currently undertaking secondary steelwork. Additionally, drainage works have commenced at Redemptorist Station.
Simultaneously, system works are progressing efficiently. Telecom installation activities at Dr. Santos and Redemptorist stations have been completed, and similar work has begun at MIA and Asia World stations.
Beyond construction progress, LRMC is actively conducting test runs of various generations of LRT-1 trains, ensuring their compatibility and readiness for operations.
The LRT-1 Cavite Extension Phase 1, upon completion, will extend the existing line by 6.2km. The first phase will connect Baclaran Station in Pasay City to Dr. Santos Station in Paranaque City. The phase 1 extension is projected to significantly reduce travel time and benefit up to 600,000 passengers daily.
LRMC President and CEO Juan F. Alfonso added, “The LRT-1 Cavite Extension Project is poised to significantly contribute to the nation’s economic growth and development by fostering improved connectivity between individuals and communities. This vital infrastructure project that LRMC is spearheading will not only bridge physical distances but also act as a catalyst for economic activity, creating new opportunities for businesses, trade, and commerce to flourish.”
LRMC remains steadfast in its commitment to deliver the LRT-1 Cavite Extension Phase 1 project on schedule and to the highest quality standards. The company will continue to keep the public informed of its progress through regular updates.